Popcorn ceilings are the most common asbestos question in Spokane. The city's housing table counts 14,216 units from the 1950s, 6,097 from the 1960s and 13,172 from the 1970s, and sprayed texture was a common ceiling finish in those decades. EPA lists textured paint and patching compounds used on walls and ceilings among the materials that may contain asbestos. A lab sample is the only way to know. Once it is known, the Spokane sequence is fixed: survey, a Notice of Intent to Spokane Clean Air at 48 square feet or more, then wet removal under containment by workers certified under L&I's asbestos rules. Skim coat and paint come after, by ordinary trades.

Typical Spokane price: $9 - $20 per sq ft (Angi, 2026); $4 - $20 per sq ft (HomeGuide); plus the Spokane Clean Air NOI fee of $250 or $500 by ceiling area · full pricing guide

Dry scraping is the mistake. EPA's list of things not to do with asbestos-containing material is short and specific: do not saw, sand, scrape or drill holes in it, and do not dust, sweep or vacuum debris that may contain it. A popcorn ceiling scraped dry does all of that at once. The texture is soft, it breaks into dust, and the dust settles on every surface in the room and into the furnace's return air. That is why a certified job is built around water and containment. The room is sealed in sheeting, the air inside is held under negative pressure, the texture is soaked so it comes off in wet sheets instead of dust, and the wet material goes into sealed, labeled bags inside the containment. The furnace is off. The room is cleaned and cleared before the sheeting comes down.

The paperwork follows the square footage. A survey by an AHERA-certified Building Inspector comes first for any contractor job. If the ceiling is asbestos-containing and a contractor will remove 48 square feet or more, the contractor files a Notice of Intent with Spokane Clean Air. From 48 to 159 square feet the notice period is 3 days and the fee is $250; one modest bedroom ceiling can land in this tier. From 160 to 4,999 square feet the notice period becomes 10 days and the fee $500, which is where a living room or several rooms together end up. Paying online adds a non-refundable convenience fee of 2.5% or a $2.00 minimum. Nothing is removed until the notice period runs. Add that wait to the lab turnaround when planning, and see the cost page for how the ranges and fixed fees stack.

Call (509) 257-4997 Get a Free Quote

When a popcorn ceiling in Spokane should be tested first

Test before any of these, not after. The ceiling gives you the age clue; the project gives you the reason.

  • The house was built before 1980, which is most of Spokane; the 1950s, 1960s and 1970s are the decades when sprayed texture was common.
  • A roof or plumbing leak above the ceiling has left stained, sagging or flaking texture that is already shedding.
  • New recessed lighting, a ceiling fan or an HVAC run is planned, since every cut hole is a disturbance under EPA's list.
  • The house is going on the market, and a scraped and skimmed ceiling is part of the plan to sell it.
  • A previous owner already scraped part of it, and the rest is coming down to match.

A lab result answers the question either way. A negative result lets an ordinary drywall contractor do the work; a positive result means the abatement process and the NOI. Either answer costs less than finding out later.

Why textured ceilings are the common Spokane case

Popcorn ceilings are the most frequent asbestos question in Spokane for two reasons: the age of the houses and the nature of the material. 68.3% of housing units inside the city were built before 1980. The postwar neighborhoods, Shadle Park, Comstock, Lincoln Heights, Audubon-Downriver and the ranch streets of Spokane Valley, where the 1970s are the largest decade, are full of ceilings finished with sprayed texture. EPA names textured paint and patching compounds used on walls and ceilings among the materials that may contain asbestos, and the joint compound under the texture is a second material that needs its own sample. The material is soft. Floor tile and cement siding hold their fibers in a binder until someone grinds them; sprayed texture crumbles at a touch, which puts it in the friable category with the tightest containment.

Almost every ceiling project disturbs it: a recessed light, a fan box, a roof leak. And almost every room is over 48 square feet, so nearly every contractor removal files a Notice of Intent. It is also the material most often taken down by the owner, where EPA's don'ts apply most directly: no sawing, sanding, scraping or drilling, and no dusting, sweeping or vacuuming the debris. With 41.2% of the city's housing units renter-occupied, a landlord repainting a unit between tenants cannot scrape it either; any work at a rental must be performed by a certified abatement contractor. The full rule and the fee ladder are in the survey rule guide.

Wet removal under containment, step by step

The room is emptied first. Furniture that cannot leave is wrapped in place, and ceiling fixtures and fans come down with their boxes sealed before any water goes up. Sheeting covers the floor and walls up to the ceiling line, the registers are sealed, and one doorway with a decontamination station becomes the only way in. The negative air unit starts before the first spray of water and runs until the clearance result is back. Removal works in sections. Workers spray a section until the texture is soaked through, wait for it to soften, and scrape it down with hand tools in wet sheets. Dry spots are the failure mode; a patch not wetted enough turns to dust, so the answer is more water, not harder scraping.

The wet material drops onto the floor sheeting and is shoveled into bags, sealed and labeled inside the containment as the work goes. Cleanup happens inside the box. The bare ceiling is wiped down, the wall and floor sheeting is folded inward so the debris side is enclosed, and the sheeting goes into bags as waste too. A visual inspection and air samples follow, with the fan still running, and only a passing result brings the last sheeting down. Every step is done by workers certified under Washington L&I's asbestos rules. The water is the same water a homeowner could use; the containment, the fan, the sealed bags and the clearance separate a compliant job from a scraped room.

What happens after the ceiling comes down

Clearance comes before anything else. The room stays sealed until the air samples are read by a lab, and the skim coat cannot start until the sheeting is down. What is left overhead is the surface the texture was sprayed onto: drywall with taped seams in a 1960s or 1970s house, plaster in an older one. It is rough, patched where fixtures were, and not paintable as it stands. The survey report decides who can touch that surface next. If the joint compound under the texture was sampled and came back negative, an ordinary drywall finisher skims, sands, primes and paints.

If the compound came back positive, sanding it is a disturbance under EPA's guidance, and the abatement scope should have said whether that compound was removed with the texture or left in place and sealed. Ask that question before the finisher arrives, not after the sanding starts. Then the ordinary trades finish the room: skim coat, sanding where the lab result allows it, primer, paint, and the recessed lights or fan box that started the whole project, now cut into a ceiling that no longer needs an NOI to drill. Those trades are priced separately from the abatement; the published ranges of $9 to $20 per square foot cover the removal only. The last step is filing: the survey, the NOI, the lab reports, the clearance and the manifest go into the house records, so the next owner knows the ceiling is gone rather than covered.

Popcorn ceilings and the NOI tiers

Three details of the Notice of Intent matter most for ceilings. First, who files: a contractor doing the work submits the NOI to Spokane Clean Air and the notice period runs from that filing; a resident owner removing texture in an owner-occupied single-family residence files nothing. Second, the unit: ceilings are measured in square feet, and the filing line is 48 square feet per structure, per calendar year, a phrase that matters when a project is split into phases. Third, the tiers against a floor plan. A closet or short hallway ceiling can sit under 48 square feet, where no notification is required, though contractor work still needs the survey and certified workers.

One bedroom lands in the 48 to 159 square foot tier: 3-day notice, $250 fee. A living room, or several rooms in one filing, moves into 160 to 4,999 square feet: 10-day notice, $500 fee. A whole house of ceilings rarely reaches the tier above 5,000 square feet at $1,250 and up; an apartment building is one structure, and the ceilings of many units add up fast. The calendar follows the tiers: survey and lab turnaround, then the NOI filing, then the 3 or 10 days, then removal, then the clearance result, then the finish trades. If the house itself is coming down, the ceiling is not filed on its own: any demolition takes a 10-day notice and a $250 NOI, and the sequence runs through the demolition page.

Remove it, cover it, or leave it

A positive lab result does not force removal. EPA's baseline is that material in good condition that will not be disturbed should be left alone, so the plan for the room decides.

Remove

The texture comes off wet under containment, and the ceiling is skimmed and painted afterward by ordinary trades. The answer when the texture is damaged, when fixtures or ductwork are going in, or when a sale should carry a clean survey. Published ranges run $9 to $20 per square foot, plus the NOI fee.

Cover it

New drywall goes over the textured ceiling, with fasteners and edges handled so the texture is not scraped or sanded. Covering keeps the material undisturbed, which is EPA's baseline for material in good condition. The texture is still there, so the survey report stays with the house for the next owner.

Leave it

Intact, not flaking, and not in the way of any planned work: leave it and keep the lab result with the house records. This is the cheapest outcome and, for an undisturbed ceiling, the one EPA's guidance points to.

Get the lab result first. The testing page explains what a survey covers; a written scope for removal should list square footage, containment, the NOI tier and the disposal route.

Popcorn Ceiling Asbestos Removal FAQs

How much does popcorn ceiling asbestos removal cost in Spokane?

Published national ranges put popcorn ceiling asbestos removal at $9 to $20 per square foot (Angi, updated August 2026) and $4 to $20 per square foot (HomeGuide). On top of that sits Spokane Clean Air's Notice of Intent fee: $250 with a 3-day notice for 48 to 159 square feet, $500 with a 10-day notice for 160 to 4,999 square feet. The survey and lab work come first, at a published testing range of $250 to $850. A written scope should state the square footage it assumes, because that number also sets the fee tier.

Can I scrape my own popcorn ceiling in Spokane?

If you own and live in the house, the rules leave it to you; that does not make it a good idea. Spokane Clean Air does not require a Notice of Intent for removal done by the resident owner of an owner-occupied single-family residence, and says a survey is recommended, though not required. Test first either way: sample the texture and get a lab result before touching it. If it is positive, EPA's guidance is not to scrape, sand or drill it and not to sweep or vacuum the debris. A rental is different: that work must be done by a certified abatement contractor.

Do all popcorn ceilings contain asbestos?

No, and no one can tell by looking. EPA lists textured paint and patching compounds used on walls and ceilings among materials that may contain asbestos, and only a lab result on a sample from that ceiling turns may into a yes or a no. The build date is a clue, not an answer: sprayed texture was common in Spokane houses of the 1950s, 1960s and 1970s, but a ceiling from those decades can test negative, and the only way to know is the sample. Treat every untested textured ceiling as suspect; that is the survey Spokane Clean Air requires before any contractor touches it.

Does a popcorn ceiling have to be removed before selling a house in Spokane?

No. Spokane Clean Air's survey and Notice of Intent requirements are triggered by renovation and demolition, not by a sale, so removal before listing is a choice rather than a rule. EPA's guidance is that material in good condition that will not be disturbed should be left alone. What a sale changes is the paperwork. A lab result in the house file tells a buyer what the ceiling is, and a buyer who plans to scrape it hires a contractor who needs the survey first. A seller who removes it before listing follows the full sequence, survey first, and hands the buyer the records instead of the question.